Fermi Project Matador signs 600 MW tenant, reportedly Amazon
The Financial Times named Amazon as the hyperscaler behind a $200 million prepayment for 600 MW at Fermi's Texas campus, sending the stock to its best day ever.

A troubled AI power developer has found a marquee name. The Fermi Project Matador campus near Amarillo, Texas, has signed commitments from an unnamed investment-grade hyperscaler for an initial 600 megawatts of power from 2027, and the Financial Times reported on Friday, November 13, that the customer is Amazon, according to Yahoo Finance and Crypto Briefing.
What happened
Fermi disclosed the deal on Thursday, November 12, with its third-quarter results. The customer committed to pay $200 million upfront plus $15 million for early site work, and a further $90 million deal for steel and building materials Fermi had lined up is still being finalized. A binding long-term lease is not yet in place, Fermi said.
Voltgrid News, which reviewed the 8-K exhibits, said the release does not state whether the prepayment has been paid or whether it would be credited against rent. Neither Fermi nor Amazon has confirmed the FT's report. Yahoo Finance said crews are due on site by December 1, with first power aimed for around mid-2027.
Investors cheered. Shares of Fermi extended Thursday's jump with their best day ever on Friday, Yahoo Finance reported, and Crypto Briefing said intraday gains were reported at 20% to 26%. Yahoo Finance, citing the FT's sources, said Amazon would likely construct its own facilities at the campus, with Fermi supplying power from its own private grid rather than a utility connection. Retail sentiment on Stocktwits turned "extremely bullish," the outlet added.
Why it matters
The deal comes after a hard year. Fermi listed in October 2025 promising a record-scale campus, but earlier talks with Amazon collapsed last December, co-founder Toby Neugebauer was ousted in April and its lease with neocloud TensorWave has now been terminated. It reported a third-quarter net loss of $141.6 million and had $286.3 million of cash at the end of September, set against debt of roughly $958 million.
For AI infrastructure, the Fermi Project Matador agreement shows hyperscalers are still paying upfront to lock in power, even as investors question capex budgets. That tension runs through recent stories such as Microsoft's neocloud review and CoreWeave's revenue beat. Fermi describes itself as pre-revenue and says the campus could ramp to about 17 gigawatts, subject to binding customer agreements. Voltgrid noted that Fermi's stated current capacity of 2.2 gigawatts includes 200 MW from Xcel Energy and turbines on order for 2028 delivery, a reminder that much of the plan is still on paper.
What's next
Fermi still needs project financing, has to satisfy year-end conditions on its 99-year land lease from Texas Tech University, and faces court challenges to its air permits, Yahoo Finance said. A signed long-term lease would be the clearest sign that the Fermi Project Matador revival is real. Yahoo Finance's report is here.
This article is for information only and is not investment advice.